We have an ongoing and active programme to
develop Monitor-Pro functionality. This is governed by the needs of our
users.
If you are interested in any of these, or have a requirement for a new development
that is not included in the list below, please let us know.
Projects in this programme are:
E-mail alerts
Status: Development completed, testing. anticipated
September 2006.
MP-5 will send emails to users and data
suppliers giving information on failed resolutions, invalid files and compliance
breaches.
Scheduled importer from third party databases
Status: Completed.
MP-5 can now with an add-in import data from
third party databases on a user-defined schedule.
Compliance Manager
Status: Under development, anticipated 2nd half 2006
With the advent of PPC in Europe, threshold
levels are being prescribed on a per-sample point basis (both upper and lower),
with a further requirement for trigger (warning) and breach levels to be set.
MP-5 can accommodate this regime. However, the new Compliance Manager is
intended to greatly reduce setup and management time.
MP-5 LT
Status: Scoping stage
A "light" version of MP-5 that will be low cost,
plus easy to install and use. It would have reduced functionality.
This could for example be bundled with instruments to manage their data, with an
upgrade option.
Restrictions would be a pre-set list of
variables to match the instrument, and no networking ability.
Report Scheduler
Status: Under development, anticipated 2nd half 2006
With MP-5 stored selections, reports are a
double click away. The next step is to automatically run and distribute
pre-stored reports to a distribution list as a pdf file, or to update an
Intra/Internet site.
Data tracker
Status: Not started.
The MP-5 Data Tracker will enable users to input
a monitoring plan. Subsequently the system will inform of both required
and missed samples.
PPC Inspection reports
Status: Completed
Our MP-5 and WebServer OPRA site inspection
system has been running for a while. There is now a requirement to expand
this for PPC Inspection reporting, as the scoring system is different.
Data link from
Incident_Reporter to MP-5
Status: Under development
An automatic link to send basic data entered
into Incident_Reporter to MP-5.
Pocket/Mobile PC data entry for MP-5
Status: Good idea stage.
This application has been suggested. Ideas
range from downloading a data entry form to the Pocket PC to GPS - and maps of
sample point locations to ensure data is taken from the correct location.
Leachate volume calculator for the MP-5 contouring add-on

Status: Proposal anticipated 1st quarter 2006.
MP-5 easily exports a 3d contour of any variable
for any date range. An extension on this is to use this contour, combined
with a site base map to provide a leachate volume.
Piper-plot for MP-5
Status: Good idea stage. This would
provide a rapid piper plot, useful for groundwater data interpretation.
Among others that could be added if required would be Durov, box whisker or
ternary.

AGS Compatibility
Status: Scoping stage
The ability to import and export could be a
useful addition. This is currently being assessed.